Vietnam

In this edition of their newsletter, Frasers report on the following:

  1. Legislative Programme of the National Assembly for 2019;
  2. Directive on the implementation of equitisation of and divestment from state-owned enterprises and enterprises having state-invested capital;
  3. Amendment of the Decision providing for the encouragement mechanism for solar power projects;
  4. Circular on wind power projects and wind power purchase agreements; and
  5. Circular on self-inspection of compliance with the labour law performed by enterprises.

 

1. Legislative Programme of the National Assembly for 2019

On 8 June 2018, Resolution No. 57/2018/QH14 passing the agenda for the issuance of laws and ordinances (Legislative Programme) during 2019 (and amending the Legislative Programme for 2018) (Resolution 57) was passed by the XIV Legislature of the National Assembly of the Socialist Republic of Vietnam (National Assembly) during its 5th session. Resolution 57 was later revised by the Standing Committee of National Assembly on 13 December 2018 with Resolution No. 613/2018/UBTVQH14 amending the Legislative Programme (Resolution 613). These resolutions offer a useful overview of the National Assembly’s Legislative Programme for 2019.

In particular, with respect to the Legislative Programme for 2019, the National Assembly is scheduled to discuss and pass some important projects such as, among others:

  1. the Law on Investment in the form of Public-Private Partnership (PPP);
  2. the amendment of the Law on Investment and the Law on Enterprises;
  3. the amendment of the Law on Securities;
  4. the amendment of the Law on Land;
  5. the amendment of the Labour Code;
  6. the amendment of the Law on Public Investment;
  7. the amendment of the Law on Environment Protection Tax;
  8. the amendment of the Law on Issuance of Legal Instruments
  9. the Law on Entry and Exit of Vietnamese Citizens; and
  10. the Law on Mediation and Dialogue at Court.

2. Directive on the implementation of equitisation of and divestment from state-owned enterprises and enterprises having state-invested capital

On 5 January 2019, the Prime Minister (PM) issued Directive No. 01/CT-TTg (Directive 01) on the implementation of equitisation of, and divestment from, state-owned enterprises and enterprises having state-invested capital (SOEs). Directive 01 is meant to reinforce and give added emphasis to the implementation of the restructuring of SOEs which was already required in the preceding legislation (being Resolution No. 12/NQ-TW, dated 3 June 2017 on continuing restructuring, innovating and enhancing the efficiency of the SOEs (Resolution 12), and Resolution No. 60/2018/QH14, dated 15 June 2018 of the National Assembly Session XIV on continuing completion and enhancing the implementation of policy and law regarding State’s capital and assets management and use at enterprises and equitisation of the SOEs (Resolution 60)). Below are some highlights of the key contents of Directive 01.

Implementation status of the restructuring of the SOEs

According to Directive 01, the restructuring and equitisation of SOEs has obtained some important achievements, such as the equitisation of 147 enterprises from 2016 to November 2018 and the collection of nearly 155 trillion VND in State capital from divestments out of various enterprises during that period.

However, Directive 01 points out some drawbacks of the equitisation of, and divestment from, the SOEs, which were mostly caused by the difficulties in evaluating corporate value, loose discipline in implementing the relevant policy and legislation, lack of accountability as well as group interests.

Requirements for enhancing the implementation of equitisation of and divestment from the SOEs

The PM requires that the equitisation of, and divestment from, the SOEs must strictly comply with the law and must ensure the transparency of the equitisation and divestment. The PM also requires that the issuance, or submission to relevant authority for issuance, of the restructuring plans must be completed, and the equitisation processes must speed-up, in accordance with the plan and timeframe of the PM.

Resolution and accountability to implement the abovementioned requirements

In order to fulfill the requirements of the equitisation of, and divestment from, the SOEs, the PM requires the following:

i) The Ministries and ministerial-level agencies must speed up and complete the legal framework serving the process of restructuring and improving the operation of SOEs after restructuring. Some notable legislation mentioned by the PM include the decree on operation of SOEs, the legislation amending and supplementing the Law on Bankruptcy, the legislation amending and supplementing the Labour Code. In addition, the State Bank of Vietnam is requested to amend and supplement Article 4 of Circular No. 32/2013/TT- NHNN, dated 26 December 2013, guiding the implementation of provisions restricting the use of foreign exchange in the Vietnamese territory (Circular 32). In particular, Directive 01 requires that Article 4 of Circular 32 must be amended to enable foreign investors to deposit/escrow in foreign currency when attending auctions for share purchase in SOEs.

ii) The Ministries, ministerial-level agencies, local authorities and SOEs must complete the approval, or submission to the relevant authorities for approval, of the restructuring plans before 15 January 2019. Such restructuring plans must specify the relevant roadmap and accountability.

iii) The Ministries, ministerial-level agencies, local authorities and SOEs and relevant entities must enhance their supervision over the process of equitisation and divestment to prevent losses to the State capital during the restructuring; enhance the listing of equitised SOEs on stock exchange; renovate corporate governance, enhance quality, efficiency and competitiveness of SOEs after equitisation and divestment as well as clarify the accountability of individuals and organisations which caused losses to the State capital and strictly handle such violations in accordance with the law.

3. New Decision on the encouragement mechanism for development of solar power projects in Vietnam

On 8 January 2019, the Prime Minister issued Decision No. 02/2019/QD-TTg (Decision 02) amending some articles of Decision No. 11/2017/QD-TTg, dated 11 April 2017 of the Prime Minister providing the encouragement mechanism for the development of solar power projects in Vietnam (Decision 11).

The most note-worthy content of Decision 02 is the change in the mechanism for purchasing and selling electricity with respect to roof solar power projects from a “net-metering mechanism using alternating-current meter systems” to a “separate delivery and receipt directions of an alternating-current [bi-directional] meter”.

Previously, Decision 11 provided that sellers of electricity generated from rooftop solar projects would sell electricity to Vietnam Electricity (EVN) based on the net-metering method with two- way electricity meters. This meant that, in a payment circle, if the amount of electricity from rooftop projects is larger than the consumption amount, the excess shall be carried forward to the subsequent payment cycle.

Due to the lack of guidelines on how to implement this clearing payment method, Decision 02 introduced another mechanism, by which (1) EVN shall pay for electricity generated from rooftop projects connected to the power grid, while (2) the sellers of electricity generated from rooftop projects shall separately pay for the electricity they have consumed from the power grid.

Decision 02 took effect as from its issuance, and is immediately applicable with respect to new projects. With respect to roof solar power projects that have been approved before the effective date of Decision 02, if (i) such projects are put into operation prior to 1 July 2019, and (ii) the meter readings taken in relation to such projects take place prior to 1 July 2019, then the new mechanism for purchasing and selling electricity under Decision 02 shall apply to such projects as well.

4. New Circular on the development of wind power projects and wind power purchase agreements

On 15 January 2019, the Ministry of Industry and Trade (MOIT) issued Circular No. 02/2019/TT

-BCT (Circular 02) providing guidance on the implementation of wind power projects and template of wind power purchase agreements (Wind PPAs). Circular 02 shall take effect as from 28 February 2019 and shall replace its preceding legislation being Circular No. 32/2012/ TT-BCT of the MOIT, dated 12 November 2012 and Circular No. 06/2013/TT-BCT of the MOIT, dated 8 March 2013, on the same matter. Below are some highlights of the key changes under Circular 02:

Development of the wind power project

Wind power projects which have not yet been listed in the master plan can be updated in the Power Development Master Plan upon assessment and approval by the relevant authorities.

Wind power projects which have already been listed in the master plan, and which require any adjustment with respect to the project implementation, will need to be reported by their investors to the relevant authorities for further appraisal and approval.

Feasibility study report

The feasibility study report for wind power projects must contain the following contents:

i) report of wind measurement;

ii) location, coordinates; land use area for a specific term and temporary land use area; sea area (if any) of the wind power project;

iii) interconnection plan, assessment of the impact of the interconnection plan on local power grid system and capacity clearance ability of the project;

iv) plan on techniques and costs for removal and settlement of the equipment of the wind power project after the project is ceased; and

v) interconnection agreement; written agreement with the relevant authorities on the location, alignment, land use area, sea area, and master plan on ground area; written confirmation of the relevant authorities on the location of offshore wind turbines (if any); written approval of the relevant authorities on clearance height.

Requirements for commencement of the construction of wind power projects

The investors are only permitted to commence constructing the wind power projects when:

i) the application dossiers on construction design have been appraised and approved in accordance with the laws;

ii) the Wind PPA is executed by the power purchaser; and

iii) there are financing agreements and capital commitments in place to ensure that the construction process can be implemented as approved.

Land use area

The land use area for the development of the projects will include: land area for examination and analysis; land use area for a specific term; and temporary land use area.

The total land use area for a specific term shall not exceed 0.35 ha/MW and the temporary land use area shall not exceed 0.3 ha/MW. Such area for land use of wind power projects must be consistent with the scale of work capacity of that project.

Process and procedure for the execution of the Wind PPAs

The investors must prepare the application dossiers proposing the execution of the Wind PPAs and submit them to Vietnam Electricity Group (EVN) in order for EVN to implement the procedures of appraisal, approval and execution of the relevant Wind PPA.

EVN shall review and execute the Wind PPAs with the power developers within 15 working days as from the date of receipt of a complete and valid dossier. The details of the application dossier for the Wind PPAs are specified under Article 16.2 of the Circular 02.

Under Circular 02, the seller and the buyer of electricity are entitled to amend the Wind PPA for the purposes of specifying the rights and obligations of the parties only, but they are not allowed to change the fundamental contents of the Wind PPA.

Works safety

Pursuant to Circular 02, the wind power project must be located at least 300m away from residential areas.

5. Circular on self-inspection of compliance with the labour law performed by enterprises

On 17 October 2018, the Ministry of Labour, Invalids and Social Affairs (MOLISA) issued Circular No. 17/2018/TT-BLDTBXH on self-inspection of compliance with the labour law performed by enterprises (Circular 17). Circular 17 took effect as from 1 January 2019 and shall replace its preceding legislation being the Regulations on Use of Self-inspection Note of Compliance with the Labour Law (Former Regulations), issued with Decision No. 02/2006/ QĐ-BLDTBXH on 16 February 2006 (Decision 02).

Circular 17 now provides a more comprehensive and detailed legal framework for self- inspection of labour law compliance by enterprises than that under the Former Regulations. Below are some highlights under Circular 17 as compared to the Former Regulations.

Obligation on periodic self-inspection

Circular 17 expressly states that the employers must conduct a self-inspection of labour law compliance at their offices/units at least once a year and must implement solutions to improve such compliance.

The self-inspection results and related documents shall be kept at the employers’ office for the monitoring, analysing and making of policies and solutions to improve compliance with labour law in enterprises.

Introducing the new online portal on compliance with labour laws

An online portal (available at tukiemtraphapluatlaodong.gov.vn) (Online Portal), shall be set up by the MOLISA for the purpose of linking, integrating and posting information channels, documents, applications and services in the labour field, for employees and employers to exploit and use.

According to Circular 17, employers shall report the results of self-inspection via the Online Portal when so requested by the labour inspector. An account on this portal shall also be created in advance by the employers to serve the reporting purpose. Previously, there was no online reporting mechanism under the Former Regulations. The employers were required to send the original of their self-inspection results directly to the labour inspector for review.

Enforcement provisions

The Former Regulations only provided that the failure to comply with the self-inspection and reporting obligations would result in such enterprise being sanctioned in accordance with the law. Circular 17 now adds that the labour inspector may decide to inspect any enterprise which does not adhere to the relevant provisions of Circular 17 and that such non-compliance to Circular 17 shall be considered as an aggravation when the state authorities impose administrative fines on the relevant enterprise. In extreme cases, if any non-compliance to Circular 17 results in serious consequences, the relevant enterprises or individuals may be prosecuted in accordance with the criminal law, and shall be sanctions in accordance with the laws.

We trust that you find this edition of our newsletter an interesting read and welcome any feedback or comments you may have on any of our topics. Our address for comments is: legalenquiries@frasersvn.com

https://www.frasersvn.com/en/

Whilst we aim to provide a useful update on new legislation, Frasers’ Newsletter does not constitute formal legal advice. Should you feel that you require further information on any of the issues in this edition of the Newsletter, please contact us at the address above or via your usual Frasers’ legal adviser.

Related Articles by Firm
Encouraging startups and SMEs in Vietnam
As well as changes at the Ministry of Industry and Trade and new measures relating to industrial parks and economic zones.
New list of state-owned enterprises to be equitised by the end of 2020
The new list includes several major SOEs, such as Agribank, Vinacomin and VNPT.
New Decree on special preferential import/export tariffs under the CPTPP
Plus recent Vietnam updates on insurance, public investment and minimum wages.
Amendment of the Law on Intellectual Property in compliance with the CPTPP
The changes follow ratification of the Comprehensive and Progressive Agreement for Trans-Pacific Partnership.
Promoting the development of Vietnam's real estate market
Plus updates on importing used machinery, amendments to the labour code and the law on public investment, and more.
New Circular guiding the restrictions on the use of foreign exchange in Vietnam
Plus updates on public private partnerships, radio and TV services, lending in foreign currencies, insurance and IP.
New Circular on capital contribution or share purchase of credit institutions in Vietnam
Plus development of rooftop solar power projects and amendments to the Law on Investment and Law on Enterprises.
Registering trademarks in Vietnam
Plus the development of solar power projects and a new circular on enterprise registration.
Vietnam update
The new region-based minimum wage, TPP agreement, corporate bonds decree and circulars on foreign exchange management for FDI and PPP.
Vietnam's Draft Law on Securities
Plus other updates, including social insurance, the Labour Code, confidentiality, e-invoices and CP-TPP ...
Related Articles
Related Articles by Jurisdiction
New Regulations Affecting Business in Vietnam
Vietnam has issued new regulations that affect PPPs, derivative securities, cross border provision of public information and employment. Here are the most important changes from each new regulation.
Notable changes introduced by the amended Labour Code 2019
The legislation includes changes to holidays, retirement age, labour contracts, trade unions and overtime.
Managing the relationship with special managers in Vietnam
Successful cooperation between a special manager and the acquirer requires the involved parties to know, name and manage this relationship ...
Latest Articles